Lake Cethana Pumped Hydro

Project Details

Project Name Lake Cethana Pumped Hydro
Status Proposed / EPBC Referral
COD (Planned / Actual) 2031
Capacity (MW) 750
Energy Storage (GWh) 15
Duration (Hours) 20
Head (m) 300
Upper Reservoir Name New upper reservoir (planned)
Lower Reservoir Name Lake Cethana
Closed-Loop or Open-Loop Closed-Loop
Location (State, Region) TAS – North-West
Coordinates ~41.6° S, 146.0° E
Developer / Owner Hydro Tasmania
Transmission Link Marinus Link
Estimated Cost (AUD) 3 billion (est.)
Funding / Partners ARENA, Hydro Tasmania
Environmental Status EPBC referral in progress
Construction Timeline 2025–2031
Job Creation (FTEs) 800
Integration Role Battery of the Nation
Website https://www.hydro.com.au
References Hydro Tasmania; ARENA

Location Map